Construction Update Brattleboro-Hinsdale Bridge

DETOUR INFORMATION: The truck detour route from VT 142 will be up Cotton Mill Hill Road, left onto South Main Street, continuing onto Fairground Road, and finally back Canal Street. Cars detouring from VT 142 should proceed up Cotton Mill Hill Rd. and make a right hand turn onto South Main St. A turnaround has been constructed south of Cotton Mill Hill Rd. on VT 142 to allow vehicles to safely navigate this corridor. A three-way stop configuration has been implemented at the Cotton Mill Hill Rd. and VT 142 intersection.


VT 142 Royal Road Weekend Work Scheduled

The installation of a 30″ Reinforced Concrete Pipe (RCP) under the railroad tracks adjacent to the intersection of Vermont Route 142 and Royal Road in Brattleboro will necessitate the contractor work 24 hours a day over the weekend beginning Friday, June 23rd and ending on Sunday, June 25th. Residents in the vicinity of the project should be advised that site lighting and construction noise will come from this location overnight on both Friday and Saturday nights. Train traffic will be suspended during this weekend closure period and is scheduled to resume again on Monday morning at 8 a.m.


Brattleboro-Hinsdale Bridge – Construction Update

The contractor will continue to work on installing new drainage systems as well as removing existing pipes and structures. Backfill of this work has begun on the southern end of VT 142 and progresses north. This fill placement is the beginning of the embankment work needed to raise the road to meet the new bridge alignment. Work on the southern MSE wall continues this week with panel placement and related backfill. Abutment A’s backwall is still in the process of being formed up with rebar being placed.


Construction Update Brattleboro-Hinsdale Bridge

The contractor will finish removing pavement and concrete roadway this week and will continue to work on installing new drainage systems as well as removing existing pipes and structures. Backfill of this work will begin on the southern end of VT 142 and progress north. Work on the southern MSE wall continues this week with panel placement and related backfill.


Brattleboro Hinsdale Bridge Construction Update – June 2

DETOUR INFORMATION: The truck detour route from VT 142 will be up Cotton Mill Hill Road, left onto South Main Street, continuing onto Fairground Road, and finally back to Canal Street. Cars detouring from VT 142 should proceed up Cotton Mill Hill Rd. and make a right hand turn onto South Main St. A turnaround has been constructed just south of Cotton Mill Hill Rd. on VT 142 to allow vehicles with significant turning radius from the north to approach Cotton Mill Hill Rd. from the south. A three-way stop configuration will also be implemented at the Cotton Mill Hill Rd. and VT 142 intersection. Motorists are advised to watch for trucks turning and reduce speed in this area.


Vermont Route 142 in Brattleboro Closed

The 90 day closure of Vermont Route 142 has begun as of today, May, 30th, 2023 and is anticipated to be completed August 28, 2023. During the closure the contractor will be working on bringing the road grade up to meet the new alignment and tie-in for the Vermont/New Hampshire Route 119 bridge over the Connecticut River.

The location of the closure is approximately 1000 feet south of the current intersection of VT 142 and VT/NH 119. Access to both Royal Road from the southern approach and to 28 Vernon Street from the north will be maintained and flaggers will be present to assist local motorists with access to these locations as needed.


Brattleboro-Hinsdale Bridge Construction Update May 26, 2023

TRAFFIC IMPACT: The planned closure for Vermont Route 142 is scheduled to be implemented on Tuesday morning, May 30, 2023 at 7 a.m. Until then, intermittent flagging operations and single lane closures will be encountered during working hours from the intersection with Royal Road and north, allowing for the entering/exiting of construction equipment to the work zones.

VT 142 will be closed for 90 days beginning north of the access to Royal Road to just south of the access to 28 Vernon Street. Flaggers will be present at both ends of the closure to assist construction vehicles into the work zone and to facilitate local traffic access to 28 Vernon Street as needed.


Brattleboro-Hinsdale Bridge Construction Update May 11

ONSTRUCTION ACTIVITIES: Drainage work has begun across from Royal Road near to the Connecticut River. The northern MSE wall work continues with the placement of panels and panel straps and the southern MSE wall may begin as early as next week with related excavation and forming of the leveling pad. The gravel wetland construction continues and is awaiting the installation of a drainage structure in order to bring this work to completion.


Brattleboro-Hinsdale Bridge – Construction Update May 4, 2023

Installation of panels and panel straps for the northern MSE wall will continue next week. Excavation for the gravel wetland south of the bridge abutment is ongoing along with the installation of drainage structures. The last of the cofferdam sheets that were used for the gravel wetland have been removed. Form work has begun at Abutment A (the Vermont abutment) for the backwall and will continue into next week with a concrete placement tentative for the end of the week.

Pile driving operations are complete at Pier 2 as of last week. However, additional work on the temporary trestle access over the CT River will need to be completed to facilitate construction equipment and the intermittent pounding of diesel hammers will continue as a part of this operation into next week. Pier 1 piles remain to be driven later this season.


Brattleboro-Hinsdale Bridge- Construction Update April 27, 2023

The contractor has finished the leveling pad installation for the northern MSE wall and will begin to set panels and the panel straps. The covered retaining wall on the west side of VT 142 will be maintained as necessary until the location can be backfilled during the summer closure period. Excavation for the gravel wetland is ongoing and coinciding installation of drainage structures has begun.

Pile driving operations are anticipated to be finished at Pier 2 by the end of this week. Pier 1 piles will be driven later this season. Additional work on the temporary trestle access over the CT River will need to be completed to facilitate construction equipment and the intermittent pounding of diesel hammers will continue as a part of this operation.


Brattleboro-Hinsdale Bridge Construction Update – April 6, 2023

The contractor has finished the tree clearing operation. Covering the existing retaining wall on the west side of VT 142 is ongoing.

On the east side of VT 142, the north MSE wall near Abutment 1 work has begun and will continue next week. In addition, work is scheduled to begin on the gravel wetland located just to the south of Abutment 1 on Monday.

As noted before, pile driving operations will continue at Pier locations 2 and 1 and intermittent pounding of diesel pile hammers is anticipated through the Summer of 2023 with Saturday work anticipated from 7 AM – 7 PM.


Brattleboro-Hinsdale Bridge Construction Update March 30

The contractor has begun working on environmental protections and controls on the west side of VT 142, preparing the retaining wall to be covered. They anticipate tree clearing operations to begin tomorrow. Tree removal will result in brief periods of full closure on VT 142 for the safety of the traveling public.

Work continues on the bridge abutment on the Vermont side where the MSE wall construction is scheduled to begin.


Hinsdale Bridge Update March 2023

TRAFFIC IMPACT: Motorists on Vermont Route 142 should be aware that construction activities are ongoing along VT 142 approximately 1000′ south of the intersection with New Hampshire Route 119. Construction vehicles will continue entering and exiting the construction site and minor flagging and delays may be encountered in this area.


Guilford Election Results

Here are the Guilford Town Meeting Australian Ballot unofficial vote totals, from the Board of Civil Authority:

Selectboard 3 Year: Verandah Porche 413; Jason Herron 91. Selectboard 2 Year: Jaime Durham 52, Tara Cheney 379, Jason Herron 75. Town Clerk: Danielle Latulippe 454. Treasurer Ellen (Elly) Majonen 454. Auditor: Lesley C. Malouin 420.

Windham Southeast School District Directors (Note: This is the Guilford Count Only; Votes from All Four Towns Will Be Combined to Determine Those Elected):

WSESD Director – Brattleboro 3 Year: Kimberly Price 234, Jaci Reynolds 111; WSESD Director – Brattleboro 2 Year: Robin Morgan 306; Rikki Risatti 47; WSESD Director – Dummerston 3 Year: Michelle Luetjen Green 178; Eva Nolan 179; WSESD Director – Putney 3 Year: Ruby McAdoo 309.


Guilford Park Project Embraces 60-day Race to Raise $20,000 for 2:1 Match

“On Your Mark, Set, Go!” According to the Guilford Park committee, the “starter pistol” has been fired for a 60-day race to raise $20,000 more dollars for the construction of the Guilford Community Park. The committee has been working for over a year on plans to build a park behind the Guilford Store, alongside the Guilford Community Church, in the center of Guilford’s Algiers Village. The park they envision is complete with a green spaces, a pavilion, a walking labyrinth, children’s play area with a slide and swings, a basketball half-court, net and fire pit.

If community members and businesses donate $20,000 by February 28, the park can qualify for a matching $40,000 Vermont Community Development grant, “Better Places Program” which will allow the park committee to have everything on their wish list, explained Dunham Rowley, one of the organizers.


Guilford Unofficial JP Election Results

Town of Guilford: General Election Nov. 8, 2022 — Justice of the Peace Vote Totals. UNOFFICIAL RESULTS. Per Guilford Board of Civil Authority.

R= Republican, D = Democratic, I = Independent. * = one of 10 elected.

*Roberta Bremmer (D) 561;
Patricia Bullock (R) 217;
Connie Burton (R) 263;
Kathy W Clark (R) 207;
Richard Clark (R) 246;


Guilford Voters: Another New JP Ballot

Guilford voters will be receiving a new ballot in the mail for the Justice of the Peace election. The ballot will be mailed to every registered voter in town by Guilford town clerk, Penny Marine, following meetings this past week of the town’s Board of Civil Authority and Selectboard. Voters should be receiving the new ballots within a few days. All previously submitted JP ballots — only the JP ballot, not the main ballot for all other offices — will not be counted and will be destroyed.

This action is a result of an error in the preparation of the main General Election ballot, which failed to include the Justice of the Peace candidates. With the approval of the Vermont Election Division of the Secretary of State’s office, the town clerk initially remediated the omission by sending new ballots to voters who requested them. A number of townspeople, however, questioned the fairness of this system.


Guilford Voters Need to Request Ballot for Justice of Peace

Registered Guilford Voters,

Due to unexpected circumstances, the Justice of the Peace candidates were not submitted in time to be placed on the original ballot for the November 8, 2022, General Election. You will not automatically receive this ballot, as you did with the original ballot. You must request this ballet if you plan to vote in advance. There are a number of contests for JP this time, so it is important to have full voter participation.


Newfane to Vote on Retail Cannabis

Newfane voters can weigh in on whether to allow retail cannabis sales at a Special Town Meeting to be held on September 20 at 6 pm at the Newbrook Fire Station. There will be in-person voting only.

An informational meeting is scheduled for Tuesday August 23 at 6 pm:  www.zoom.us/joinameeting   ID: 972 2791 1757   Passcode 352680