Construction Update Brattleboro-Hinsdale Bridge – April 25, 2024
The northbound shoulder will continue to be closed all week long and motorists are advised to watch for vehicles entering and exiting the construction site.
Delivery of steel to the abutment site on Vermont Route 142 is currently scheduled for Monday, April 29th, and Wednesday, May 1st. The delivery route is planned to provide direct access from the south along VT 142 from Massachusetts Route 10. Flaggers and Uniformed Traffic Officers will be available to assist with the delivery, however it is not anticipated to require a lane closure. When the steel is ready to be moved from the truck to the bridge, a brief hold of all traffic on VT 142 will be required.