Construction Update Brattleboro-Hinsdale Bridge – July 3, 2024

Superstructure work continues to advance toward Vermont as the contractor continues formwork for overhangs. Shear stud placement and grouting have been completed and rebar installation will continue in earnest beginning on Monday, July 8th after the holiday. Dewatering and treatment tanks that have been awaiting removal have been tentatively scheduled to be cleaned and taken away sometime next week.


Construction Update Brattleboro-Hinsdale Bridge Update June 27, 2024

Work continues to progress toward the Vermont abutment on the remaining overhang formwork, placing shear studs into girders, grouting deck panels, and placing rebar. Grouting of deck panels in Vermont will take place on Monday, July 1st, with the concrete delivered to a pump truck located beneath the bridge in the Barrows & Fisher’s property.


Construction Update Brattleboro-Hinsdale Bridge – June 20, 2024

Increased construction traffic is anticipated adjacent to the work zone on Vermont Route 142 while the large crane is disassembled. Motorists should remain vigilant.

Due to current work on New Hampshire Route 119 associated with the project, the eastbound lane shift on NH 119 shortly after traveling over the twin bridges remains active. Signs and barrels are in place to assist motorists through the work zone.


Construction Update Brattleboro-Hinsdale Bridge – May 30, 2024

Last week’s operations of installing deck panels, forms for drainage scuppers within the deck, and brackets and forms for overhangs continue to progress westerly to reach the Vermont abutment. Tensioning of the bolts on cross-braces and steel diaphragms is being finalized. Cleaning and removal of the components of the water treatment system used at Pier 1 remains on hold.


Construction Update Brattleboro-Hinsdale Bridge – May 23, 2024

Crews continue to install deck panels, forms for drainage scuppers within the deck, and brackets and forms for overhangs as they progress westerly to reach the Vermont abutment. Welding the shear studs to the beams will also advance into Vermont next week. Tensioning of the bolts on the recently erected structural steel will be substantially complete this week. Cleaning and removal of the components of the water treatment system used at Pier 1 is on hold.


Construction Update Brattleboro-Hinsdale Bridge May 16, 2024

No traffic impacts are anticipated on Vermont Route 142 next week, however the work zone remains active and motorists should watch for construction vehicles entering and exiting the work site.

Due to current work on New Hampshire Route 119 associated with the project, vehicles traveling eastbound into New Hampshire from Vermont should expect a newly line-striped lane shift on NH 119 shortly after traveling over the twin bridges. Signs and barrels are in place to assist motorists through the work zone.


Construction Update Brattleboro-Hinsdale Bridge – April 25, 2024

The northbound shoulder will continue to be closed all week long and motorists are advised to watch for vehicles entering and exiting the construction site.

Delivery of steel to the abutment site on Vermont Route 142 is currently scheduled for Monday, April 29th, and Wednesday, May 1st. The delivery route is planned to provide direct access from the south along VT 142 from Massachusetts Route 10. Flaggers and Uniformed Traffic Officers will be available to assist with the delivery, however it is not anticipated to require a lane closure. When the steel is ready to be moved from the truck to the bridge, a brief hold of all traffic on VT 142 will be required.


Construction Update Brattleboro-Hinsdale Bridge – April 18, 2024

One way alternating traffic patterns with flaggers will be implemented on Vermont Route 142 adjacent to the construction site on Monday and Tuesday next week. The northbound shoulder will be closed all week long and motorists are advised to watch for vehicles entering and exiting the construction site.

Delivery of steel to the abutment site on VT 142 is currently scheduled for Wednesday, April 24th, Monday, April 29th, and Wednesday, May 1st. The delivery route is planned to provide direct access from the south along VT 142 from Massachusetts Route 10. Flaggers and Uniformed Traffic Officers will be available to assist with the delivery, however it is not anticipated to require a lane closure. When the steel is ready to be moved from the truck to the bridge, a brief hold of all traffic on VT 142 will be required.


Closure Reminder: Brattleboro-Hinsdale Bridge Project

A short duration closure (approximately 15 minutes) of VT/NH 119 can be expected today April 10th, tomorrow April 11th, Monday April 15th, and Wednesday April 17th at 11:00 a.m. for structural steel deliveries.

The delivery route of the structural steel to the Barrows and Fisher yard where the Pier 1 site is located will be along New Hampshire and Vermont Route 119 to Depot Street. This impact will include a short duration closure (approximately 15 minutes) of the twin bridges beginning at the intersection of Bridge Street to Canal Street, Main Street, and Vermont Route 142. Uniformed Traffic Officers will be located at the intersection’s entrance to Bridge Street during the closure period.


Construction Update Brattleboro-Hinsdale Bridge – April 3, 2024

Delivery of steel girders to Pier 1 is scheduled for Tuesday through Thursday, April 9th, 10th, and 11th, and Monday, April 15th.

The delivery route will be along New Hampshire and Vermont Route 119 to Depot Street. This impact will include a short duration closure (approximately 15 minutes) of the twin bridges beginning at the intersection of Bridge Street to Canal Street, Main Street, and Vermont Route 142. Uniformed Traffic Officers will be located at the intersection’s entrance to Bridge Street during the closure period. All deliveries are tentatively set for 1:00 p.m. to accommodate the train schedule.


Construction Update Brattleboro-Hinsdale Bridge – March 28, 2024

The contractor’s crews have been accessing the Vermont Abutment off of Vermont Route 142 and will continue to access this location next week. No traffic impacts are anticipated, but motorists are advised to watch for vehicles, including concrete trucks, entering and exiting the construction site.

Delivery of steel girders to Pier 1 is scheduled for Tuesday through Thursday, April 9th, 10th, and 11th, and Monday, April 15th.


Construction Update Brattleboro-Hinsdale Bridge – March 21, 2024

Work has continued on the cap for Pier 1 with the rebar being flown into place and tied atop the stem. Form work for the cap will be completed, bearing seats fully constructed, detail work finished, and everything fully adjusted to match plan location and elevation prior to the scheduled concrete placement next Tuesday.

Additional crews may begin work on the drainage installation required in the Barrows and Fisher yard late next week.


Construction Update Brattleboro-Hinsdale Bridge – March 15, 2024

Crews have stripped all forms for the Pier 1 footing and stem. The footing has now been backfilled with clean stone and the cofferdam sheets have been pulled. Work has begun on the cap for Pier 1 and forms are being placed. Next Tuesday, the cap rebar will be placed on top of the stem and the remainder of the week will be spent tying the cap to the stem, installing formwork, and making final adjustments to be ready for concrete. Another crew may begin work on drainage installation required in the Barrows and Fisher yard next week as well.


Construction Update Brattleboro-Hinsdale Bridge – March 7, 2024

The placement of 105 CY of concrete for the Pier 1 stem was accomplished efficiently yesterday and is now in its cure period. Crews are continuing work on the Pier 1 cap and will begin stripping the footing forms and conducting clean up of the Barrows and Fisher site. An additional crew is back at the VT Abutment site to make improvements to the bearing seats prior to structural steel placement. The pedestals will need to be brought up in elevation approximately 1.5″ so they will be chipped out and re-cast cleanly.

Next week, if early strength tests are adequate, work will begin on placing the Pier 1 cap steel and forms atop the stem, stripping stem formwork, possibly backfilling the footing, and removing the cofferdam sheets.


Construction Update Brattleboro-Hinsdale Bridge March 1, 2024

Recent favorable weather has helped the cure of the footing at Pier 1 and the strength of the concrete has allowed crews to move forward with the work on the Pier 1 stem and cap. As the stem rebar is placed and tied, form walls and corners will be set. Once the stem rebar is complete, crews will finish the cap rebar. The next concrete placement will be for the Pier 1 stem and is scheduled for Wednesday, March 6th.