Construction Update Brattleboro-Hinsdale Bridge Update – August 1, 2024
Multiple concrete placements are scheduled for the next 3 weeks for the bridge approach from VT 142 as well as the sidewalks and rail copings. A placement for sidewalk and curb is scheduled for Monday, and the Vermont approach slab is to be placed Wednesday. Both will require multiple truckloads of concrete.
Work on cleaning and removing the remaining two tanks from the Pier 1 dewatering treatment system will resume next week. Finish work of berm repair, grading, and paving in the Barrows and Fisher yard around Pier 1 also remains.