Construction Update Brattleboro-Hinsdale Bridge December 12, 2024

Crews are continuing to clean up and remove forms on the bridge under a shoulder closure as weather allows. Advance warning signs for the shoulder closure will be in place to notify the traveling public of the operation. Permanent pavement markings are tentatively scheduled on NH 119 for Wednesday, December 18th just east of the new bridge. This work is weather dependent and will result in short delays and one-way alternating traffic.


Christmas Sale of West River Railroad Books

The Historical Society of Windham County located in Newfane, Vt is selling West River Railroad Books at a discounted price in time for Christmas.   The West River Railroad ran from Brattleboro to South Londonderry for the period of 1880 to 1936,  the Historical Society has purchased the Newfane Depot which was one of 10 stations along the route.  The depot has been refurbished and is now a museum for the railroad.


Construction Update Brattleboro-Hinsdale Bridge – December 6, 2024

The new bridge for New Hampshire/Vermont Route 119 is now open. Motorists should use caution while navigating the new traffic pattern. Pedestrians should continue to use existing accommodations on the old bridges as the new bridge will remained closed to pedestrians until Spring of 2025.

On days when the weather is good enough to work on the bridge deck, crews will be working under a shoulder closure. Otherwise, no interruptions to NH/VT 119 and Vermont Route 142 traffic are planned for next week.


Brattleboro – Hinsdale Bridge Opening Today

The new bridge for New Hampshire/Vermont Route 119 will open to motor vehicle traffic around 2:00 p.m. today!

Due to inclement weather forecasted for tomorrow, the bridge is scheduled to be open by 2:00 p.m. today. Crews are currently working on eradicating the permanent pavement markings that need to be removed and re-striping on the New Hampshire side.


Brattleboro-Hinsdale Bridge Opening Final Reminder

Motorists should watch for message boards throughout the area indicating the new bridge is open.

A new traffic pattern is scheduled to be in place in Brattleboro by the end of the day Thursday, December 5th. Barricades will be set up on Bridge Street to encourage local traffic only. Eastbound travelers to VT/NH 119 will need to turn onto Vermont Route 142 (Vernon Street) and access the new bridge at the new signalized intersection. Westbound traffic on VT/NH 119 will need to turn onto VT 142 north to proceed to U.S. Route 5 (Canal Street).


Construction Update Brattleboro-Hinsdale Bridge Nov 27, 2024

Motorists are advised to watch for the new traffic pattern to be implemented next week.

TRAFFIC IMPACTS:

The new bridge for New Hampshire/Vermont Route 119 is scheduled to open next week by the end of the day on Thursday, December 5th. Message boards throughout the area will indicate when traffic on the new bridge is active. All traffic wishing to access NH/VT 119 will need to turn onto Vermont Route 142 and access the new bridge at the new signalized intersection. Pedestrians should continue to use existing accommodations on the old bridges.


Brattleboro-Hinsdale Bridge Opening Information

The new bridge for New Hampshire/Vermont Route 119 is scheduled to be open to motor vehicle traffic by the end of the day December 5th, 2024.

TRAFFIC IMPACTS:

A new traffic pattern is scheduled to be in place in Brattleboro by the end of the day Thursday, December 5th. Barricades will be set up on Bridge Street to encourage local traffic only. Eastbound travelers to VT/NH 119 will need to turn onto Vermont Route 142 (Vernon Street) and access the new bridge at the new signalized intersection. Westbound traffic on VT/NH 119 will need to turn onto VT 142 north to proceed to U.S. Route 5 (Canal Street).


Construction Update Brattleboro-Hinsdale Bridge – November 15, 2024

Crews have begun working on fence and guardrail along VT 142 and the new bridge and this work will continue into next week. While the installation of traffic signals and lights has been completed, it’s anticipated that crews will continue working on the installation of solar panels and coordinating the timing of the signals with the Town and State. Paving of the driveway entrance to 28 Vernon Street and some potholes in the parking lot was completed this past week.

Sign crews will continue placing signs for the new bridge next week. The signs will be covered until the bridge is ready to open. This crew will be accessing shoulders along approach routes to the project in a mobile work zone with a uniformed traffic officer.


Brattleboro-Hinsdale Bridge Opening Information – December 5th, 2024

The new bridge for New Hampshire/Vermont Route 119 is scheduled to be open to motor vehicle traffic by December 5th, 2024.

A new traffic pattern is scheduled to be in place in Brattleboro by the end of the day Thursday, December 5th. Barricades will be set up on Bridge Street to encourage local traffic only. Eastbound travelers to VT/NH 119 will need to turn onto Vermont Route 142 (Vernon Street) and access the new bridge at the new signalized intersection. Westbound traffic on VT/NH 119 will need to turn onto VT 142 north to proceed to U.S. Route 5 (Canal Street).

Pedestrian traffic should continue to utilize the existing accommodations on the truss bridges. The new bridge will remain closed to pedestrians until the Spring of 2025 due to continued contractor operations within the work zone.


Construction Update Brattleboro-Hinsdale Bridge – November 7, 2024

Paving of the driveway entrance to 28 Vernon Street and some potholes in the parking lot is scheduled to take place one day next week as weather allows. Delays entering and exiting the lot may be encountered during this operation as the pavement must cool to a certain temperature for traffic to drive on it.

Installation of traffic signals and lighting at the new intersection of VT 142 and VT/NH 119 has been mostly completed with the exception of some solar power cells for the lights. This work will continue into next week. Coordination and timing of the signal with Brattleboro Department of Public Works and the Vermont Agency of Transportation signal operations will continue.

Sign crews will continue placing signs for the new bridge next week. The signs will be covered until the bridge is ready to open. This crew will be accessing shoulders along approach routes to the project in a mobile work zone with a uniformed traffic officer.


Guilford Unofficial Election Results

Town of Guilford, Vermont — 2024 General Election — Local Unofficial Results
Guilford turned out: 1400 voted, of 1830 on the voter checklist.

State Senator (Guilford Totals Only) Windham 1 (Guilford Total Only) &
Guilford Justice of the Peace Contests

These are Unofficial Results provided as a convenience as the polls close. Official totals will be posted on the Town website shortly, and transmitted to the Vt Secretary of State


Construction Update Brattleboro-Hinsdale Bridge – October 24, 2024

Crews will begin to install the traffic signals needed for the project beginning Monday, October 28th. Sign crews will begin placing signs for the new bridge next week as well. The signs will be covered until the bridge is ready to open. This crew will be accessing shoulders along approach routes to the project in a mobile work zone with a uniformed traffic officer.

Clean up continues on all parts of the project while the contractor removes overhang forms and strips, patches (if needed), and waterproofs exposed concrete. Removal of the temporary trestle, with its intermittent noise from the diesel hammer, is an ongoing process.


Construction Update Brattleboro-Hinsdale Bridge October 17, 2024

Final pavement was placed on VT 142. Crews will be mobilizing next week to work on the signal system in the intersection of VT 142 and VT/NH 119. Crews will also be working on guardrail and fencing systems. Work will continue at the Pier 1 site on the Barrows and Fisher property while the drainage in the area is planned and the finalized.

Clean up continues on all parts of the project while the contractor continues to take advantage of the weather to strip, patch (if needed), and waterproof exposed concrete. Removal of the temporary trestle, with its intermittent noise from the diesel hammer is an ongoing process.


Hinsdale Bridge, Route 119 Closure

The Hinsdale, NH bridge on Route 119 is currently closed due to an emergency incident.  The traffic lights on lower Main Street are on flash and access to NH Route 119 is closed at the Bridge and Main Street intersection.  Motorists should seek alternate routes.


Construction Update Brattleboro-Hinsdale Bridge -October 10, 2024

Concrete for the last moment slab was placed last week. Concrete will still be needed for some sign bases and sidewalk work, so concrete trucks will still be using local routes to reach the construction site when needed, and from time to time their proximity to a traveled road may require alternating one lane traffic controlled by flaggers.

The bridge was paved this week. Work on the Vermont approach to the bridge is to be completed this week. Paving there is scheduled to resume Monday, October 14, and should take two days. Final striping of VT 142 and the bridge is set for Thursday, October 17th. The reconfiguration of VT/NH 119 will require some temporary pavement markings at a later date when the bridge is ready to be opened to traffic.


Construction Update Brattleboro-Hinsdale Bridge – October 3, 2024

Concrete for two of the three remaining moment slabs was placed this week, and the last is set to be placed Friday, October 4th. This is the last structural concrete needed for the project! Concrete will still be needed for some sign bases and sidewalk work, so concrete trucks will still be using local routes to reach the construction site when needed, and from time to time their proximity to a traveled road may require alternating one lane traffic controlled by flaggers.

The crew placing the waterproof membrane on the bridge deck is completing their work this week. Paving will begin Tuesday, October 8th, with a 1” layer of Bridge Base pavement followed by the 1 ½” bridge wearing course of asphalt.

Crews continue to take advantage of the weather and strip, patch (if needed), and waterproof exposed concrete as clean-up continues. This includes stripping of overhang forms.


Dummerston Leadership Council Meeting Minutes September 19, 2024

1. Were appropriate reporting channels followed? Complaints bypassed process and went directly to the boardroom.

2. Was the need to maintain a distinction between the administrative role of the administrators and the policy making role of the board adhered? Board members inserted their personal stance and directly requested change at a school level.


Construction Update Brattleboro-Hinsdale Bridge Update September 26, 2024

Construction traffic can get onto the bridge from the Vermont end so motorists need to be aware of an increase in construction vehicles on VT 142, especially as they slow to turn onto the bridge.

This week, concrete was placed for the New Hampshire expansion joint as well as the adjoining deck end and overhangs, so the moment slabs adjacent to VT 142 are the last structures of the project in need of concrete. That placement of concrete for the moment slabs is set to be done Monday, September 30th. The proximity of the concrete trucks to VT 142 may require alternating one lane traffic controlled by flaggers.


Construction Update Brattleboro-Hinsdale Bridge September 20, 2024

Work is progressing steadily at the Vermont abutment. The expansion joint is now able to support vehicles, so construction traffic can now get onto the bridge, but only from the Vermont end. This will mean an uptick in construction vehicle traffic on VT 142.

This week, work was shifted to forming and finishing the New Hampshire expansion joint, so the formwork and rebar for the moment slabs adjacent to VT 142 will continue to be installed next week. Placement of concrete for the moment slabs should begin next week and carry into the following week. While the bulk of this work is away from the VT 142 roadway, the proximity of the concrete trucks to the road may require alternating one lane traffic controlled by flaggers.