Public Invited to ‘Trail Talk’ To Be Held for I-91 Brattleboro Bridge Project

The PCL+FIGG Team will conduct the next on-site “trail talk” for the Public on Saturday, June 13, 2015. There has been a lot of progress at the I-91 Brattleboro Bridge project site, which will be shared with attendees. The talks will originate at the West River Trail near the marina. The trail talk will be led by Caleb Linn, Project Manager for PCL (lead contractor) and William Johnson, Senior Quality Engineer for FIGG (bridge designer).

Interested participants should meet the PCL+FIGG Team at the West River Trail trailhead on Saturday, June 13, 2015, at 8 a.m. and the talk will begin at 8:15 a.m. Participants will walk the trail to the I-91 bridge site, so please wear appropriate clothing and footwear.


I-91 Brattleboro Bridge Replacement Project Update: Week of June 7

The Strolling of the Heifers Weekend

We coordinated w/ the organizers, and hope that bridge construction did not affect the festival. We hope everyone had a wonderful time!

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.


I-91 Brattleboro Bridge Replacement Project Update: Week of May 31

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

Night work adjacent to Route 30 will continue this week, but will not affect traffic.

The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 will be reduced to a single lane intermittently both day and night, with flaggers regulating traffic within the work zone.


Red Clover Commons Work to Start on Thursday May 28th, 2015

Brattleboro Housing Partnerships and Housing Vermont are pleased to announce that demolition and environmental remediation work will begin at 30 Fairground Rd. on Thursday, May 28.

The work will focus on demolition of the block building toward the back of the lot, removal of materials still on the site and preparation of the entire area for construction. It is anticipated that the work will take at least two weeks.

Construction of the Red Clover Commons building and site will commence shortly after the demolition work is finished. The construction will take approximately 12 months. Once completed, residents from Melrose Terrace will begin to be moved to the new development.


I-91 Brattleboro Bridge Replacement Project Update: Week of May 17

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

Night work adjacent to Route 30 will continue this week, but will not affect traffic.

The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 will be reduced to a single lane intermittently both day and night, with flaggers regulating traffic within the work zone.


I-91 Brattleboro Bridge Replacement Project Update: Week of May 10

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

Night work adjacent to Route 30 will continue this week, but will not affect traffic.


Safety Improvement Project at Western Avenue, Union Hill, Cedar Street

A Safety Improvement Project at the intersection of Western Avenue, Union Hill, and Cedar Street will begin on Tuesday, May 5, 2015 with a projected completion in June, approximately six weeks. The Department of Public Works will be working on the project from 7:00 a.m. until 3:30 p.m. daily.

During this construction period, Union Hill and Cedar Street will be closed at the intersection and pedestrian traffic will be allowed via a temporary crosswalk.


I-91 Brattleboro Bridge Replacement Project Update: Week of May 3

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

Night work adjacent to Route 30 will continue this week, but will not affect traffic.

The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 will be reduced to a single lane intermittently both day and night, with flaggers regulating traffic within the work zone.


I-91 Brattleboro Bridge Replacement Project Update: Week of April 26

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

Night work adjacent to Route 30 will continue this week, but will not affect traffic.

The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 will be reduced to a single lane intermittently both day and night, with flaggers regulating traffic within the work zone.


I-91 Brattleboro Bridge Replacement Project Update: Week of April 19

I-91

On Tuesday, April 21, there will be a formal inspection of the I-91 Bridge. Daylight is needed for the inspection, so the bridge will be closed from approximately 8:00 AM to 5:00 PM. At the same time, the PCL team will repair potholes that developed over the winter. I-91 will be closed between Exits 2 and 3 both northbound and southbound. Traffic will be detoured onto VT Route 5.

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.


I-91 Brattleboro Bridge Replacement Project Update: Week of April 12

I-91

On Tuesday, April 21, there will be a formal inspection of the I-91 Bridge. Daylight is needed for the inspection, so the bridge will be closed from approximately 8:00 AM to 5:00 PM. At the same time, the PCL team will repair potholes that developed over the winter. I-91 will be closed between Exits 2 and 3 both northbound and southbound. Traffic will be detoured onto VT Route 5.

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.


I-91 Brattleboro Bridge Replacement Project Update: Week of March 29

New Text Alert System

A new text alert system for the Brattleboro Bridge Replacement Project makes it possible to receive text notifications of:

• Interstate ramp closings,

• Closings of I-91,

• Closings of VT Route 30 (but not single lane closings of Rt 30), and

• Any other situations regarding time sensitive project-related traffic issues.

People can sign up for this service by texting 313131 with the keyword “I91Brat”, or by using the signup widget on the project website www.i91brattleborobridge.com.


I-91 Exit 3 Closed Sunday

This Sunday, the project team will close both the northbound and southbound Exit 3 on-ramps to reduce congestion on I-91 Southbound caused by merging traffic. Because of highway logistics, we need to close both northbound and southbound on-ramps. Local southbound traffic will be rerouted to Route 5 south to Exit 2 or 1, and local northbound traffic will be rerouted to Route 5 north to Exit 4. Sheriff officers will assist in directing traffic. The on-ramps at Exit 3 will be closed from approximately noon to 7:00 pm.


Reminders: I-91 Exit 3 On Ramps Closed Sunday Noon to 7pm and Heavy Weekend Traffic

A reminder that this Sunday from noon to 7:00 pm we will close both the northbound and southbound Exit 3 on-ramps to reduce congestion on I-91 Southbound caused by merging traffic. Please use Vt Route 5 as an alternate route.

And please expect heavy traffic and resulting delays between Exits 2 and 3 on I-91 this weekend. Traffic is likely to be heaviest northbound on Friday afternoon and evening, and southbound on Sunday afternoon and evening. Those with flexible travel plans should consider alternate travel times and/or routes. Please also consider using Vt Rt 5 as an alternate route.


I-91 Exit 3 Ramps To Close Sunday

This Sunday, we will close both the northbound and southbound Exit 3 on-ramps to reduce congestion on I-91 Southbound caused by merging traffic. Because of highway logistics, we need to close both northbound and southbound on-ramps. Local southbound traffic will be rerouted to Route 5 south to Exit 2 or 1, and local northbound traffic will be rerouted to Route 5 north to Exit 4. Sheriff officers will assist in directing traffic. The on-ramps at Exit 3 will be closed from noon to 7:00 pm.


Public Invited to ‘Trail Talk’ To Be Held for I-91 Brattleboro Bridge Project

The PCL+FIGG Team will conduct the next on-site “trail talk” for the Public on Saturday, March 14, 2015. There has been a lot of progress at the I-91 Brattleboro Bridge project site, which will be shared with attendees. The talks will originate at the West River Trail near the marina. The trail talk will be led by Caleb Linn, Project Manager for PCL (lead contractor) and William Johnson, Senior Quality Engineer for FIGG (bridge designer).

Interested participants should meet the PCL+FIGG Team at the West River Trail trailhead on Saturday, March 14, 2015, at 8 a.m. and the talk will begin at 8:15 a.m. Participants will walk the trail to the I-91 bridge site, so please wear appropriate clothing and footwear.


Delays on I-91 Expected Between Exit 2 & 3

Please expect heavy traffic and resulting delays between Exits 2 and 3 on I-91 this weekend. Traffic is likely to be heaviest northbound on Friday afternoon and evening, and southbound on Sunday afternoon and evening. Those with flexible travel plans should consider alternate travel times and/or routes. Please also consider using Vt Rt 5 as an alternate route.


I-91 Brattleboro Bridge Replacement Project Update: March 7 -14

One-Way Traffic: This Saturday, March 7, we need to make a major concrete placement adjacent to Route Consequently, traffic on Vermont Route 30 within the work zone will be reduced to one-way beginning at 5:30 AM, and continuing to approximately 5:30 PM. Flaggers will be present to control traffic.

One-Way Traffic: The completion of the realignment or Route 30 is tentatively scheduled for completion on Monday, March 9. Traffic on Route 30 will be one-way during the day on Monday, as workers repaint the road. This work is weather dependent, so may need to be rescheduled.


I-91 Brattleboro Bridge Replacement Project Update: Week of March 1

Route 30: One-Way Traffic and Night Work: Night work on the new bridge Route 30 will be conducted Monday night, March 2nd through Friday night, March 6th. Traffic on Vermont Route 30 within the work zone will be reduced to one-way starting later this week, so that the team can work on a very slight realignment of Route 30. Work will be conducted during daylight hours only, and flaggers will be present to control traffic. The work will be completed by the end of next week.

I-91 Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.