I-91 Brattleboro Bridge Replacement Project Update: Week of March 1
Route 30: One-Way Traffic and Night Work: Night work on the new bridge Route 30 will be conducted Monday night, March 2nd through Friday night, March 6th. Traffic on Vermont Route 30 within the work zone will be reduced to one-way starting later this week, so that the team can work on a very slight realignment of Route 30. Work will be conducted during daylight hours only, and flaggers will be present to control traffic. The work will be completed by the end of next week.
I-91 Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.