Main Street Sidewalk Update #5
This is our fifth update on the Main Street Sidewalk Project. For those of you who are regularly downtown, you will have seen a flurry of activity!
This week curbing and sidewalk was removed all the way down to Centre Congregational Church. The contractor was able to install much of the conduit in that area for the underground electrical lines for the street lights. Green Mountain Power has completed the installation of the bases for the new light poles. The contractor has also began replacing some of the ramps and sidewalks in the areas across driveways on the northern end of the project. Our job site even survived the rain storm on Tuesday!