Construction Update Brattleboro-Hinsdale Bridge Update June 27, 2024

Construction Update

Brattleboro-Hinsdale

BF A004(152)

DATE: Thursday, June 27, 2024

TRAFFIC IMPACTS:

Motorists should remain alert for construction traffic entering and exiting the work zone from Vermont Route 142 and Depot Street.

Due to current work on New Hampshire Route 119 associated with the project, the eastbound lane shift on NH 119 shortly after traveling over the twin bridges remains active. Signs and barrels are in place to assist motorists through the work zone.

Looking east from the site occupied by the large crane on the Vermont abutment.

CONSTRUCTION ACTIVITIES:

Work continues to progress toward the Vermont abutment on the remaining overhang formwork, placing shear studs into girders, grouting deck panels, and placing rebar. Grouting of deck panels in Vermont will take place on Monday, July 1st, with the concrete delivered to a pump truck located beneath the bridge in the Barrows & Fisher’s property.

LOCATION:

The Hinsdale, NH to Brattleboro, VT bridge project will replace the existing twin truss bridges on New Hampshire Route 119 over the Connecticut River with a single, new structure approximately 1800′ long. On the Vermont side, the new structure will begin on Vermont Route 142 – about 1000′ south of the current intersection of VT 142 and NH 119. The new configuration will connect to NH 119 in New Hampshire east of the George’s Field Road/NH 119 intersection.

Unanticipated delays at a couple of the piers have adjusted the project completion date from Fall 2024 to Summer 2025.

PROJECTED COMPLETION: June 30, 2025

Contact Information:

Name – Bethany Oprendek

Phone – 802.267.4044

Email – bethany@bbo-enterprises.com