Construction Update Brattleboro-Hinsdale Bridge – May 30, 2024

Construction Update

Brattleboro-Hinsdale

BF A004(152)

DATE: Thursday, May 30, 2024

TRAFFIC IMPACT:

Construction vehicles will continue to enter and exit the work zone off of Vermont Route 142 next week and motorists should remain vigilant in this area.

Due to current work on New Hampshire Route 119 associated with the project, vehicles traveling eastbound into New Hampshire from Vermont should expect a newly line-striped lane shift on NH 119 shortly after traveling over the twin bridges. Signs and barrels remain in place to assist motorists through the work zone.

CONSTRUCTION ACTIVITIES:

Last week’s operations of installing deck panels, forms for drainage scuppers within the deck, and brackets and forms for overhangs continue to progress westerly to reach the Vermont abutment. Tensioning of the bolts on cross-braces and steel diaphragms is being finalized. Cleaning and removal of the components of the water treatment system used at Pier 1 remains on hold.

LOCATION:

The Hinsdale, NH to Brattleboro, VT bridge project will replace the existing twin truss bridges on New Hampshire Route 119 over the Connecticut River with a single, new structure approximately 1800′ long. On the Vermont side, the new structure will begin on Vermont Route 142 – about 1000′ south of the current intersection of VT 142 and NH 119. The new configuration will connect to NH 119 in New Hampshire east of the George’s Field Road/NH 119 intersection.

Unanticipated delays at a couple of the piers have adjusted the project completion date from Fall 2024 to Summer 2025.

PROJECTED COMPLETION: June 30, 2025

Contact Information:

Name – Bethany Oprendek

Phone – 802.267.4044

Email – bethany@bbo-enterprises.com