Construction Update
Brattleboro-Hinsdale
BF A004(152)
DATE: Thursday, December 14, 2023
TRAFFIC IMPACT:
No traffic impacts are scheduled for next week along the Vermont Route 142 corridor.
Temporary Shoring Tower construction.
CONSTRUCTION ACTIVITIES:
The Pier 1 cofferdam has been installed. The construction of the temporary shoring tower between Piers 1 and 2 will continue over the course of next week. The de-watering and water treatment system is up and running, however, the volume of water has exceeded the capacity of the system. Additional measures to excavate and then place a concrete tremie seal in the cofferdam are being completed – hopefully by tomorrow – which should allow the successful de-watering of the cofferdam to begin next week. If de-watering can be accomplished by next week, crews will begin to work on cutting the piles to elevation and placing rebar cages in anticipation of concrete.
LOCATION:
The Hinsdale, NH to Brattleboro, VT bridge project will replace the existing twin truss bridges on New Hampshire Route 119 over the Connecticut River with a single, new structure approximately 1800′ long. On the Vermont side, the new structure will begin on Vermont Route 142 – about 1000′ south of the current intersection of VT 142 and NH 119. The new configuration will connect to NH 119 in New Hampshire east of the George’s Field Road/NH 119 intersection.
PROJECTED COMPLETION: Fall 2024.
Contact Information:
Name – Bethany Oprendek
Phone – 802.267.4044
Email – bethany@bbo-enterprises.com