Construction Update
Brattleboro-Hinsdale
BF A004(152)
DATE: Thursday, December 7, 2023
TRAFFIC IMPACT:
No traffic impacts are scheduled for next week along the Vermont Route 142 corridor.
CONSTRUCTION ACTIVITIES:
Pipe pile clean out has been completed and the crew is mobilizing the equipment for that operation offsite. The construction of the temporary shoring tower between Piers 1 and 2 will continue over the course of next week. Work on the Pier 1 cofferdam sheets began earlier this week and should be completed in the next few working days. De-watering and excavation to subgrade are both operations that are scheduled into next week.
LOCATION:
The Hinsdale, NH to Brattleboro, VT bridge project will replace the existing twin truss bridges on New Hampshire Route 119 over the Connecticut River with a single, new structure approximately 1800′ long. On the Vermont side, the new structure will begin on Vermont Route 142 – about 1000′ south of the current intersection of VT 142 and NH 119. The new configuration will connect to NH 119 in New Hampshire east of the George’s Field Road/NH 119 intersection.
PROJECTED COMPLETION: Fall 2024.
Contact Information:
Name – Bethany Oprendek
Phone – 802.267.4044
Email – bethany@bbo-enterprises.com