Construction Update Brattleboro-Hinsdale Bridge Dec 21, 2023

Construction Update

Brattleboro-Hinsdale

BF A004(152)

DATE: Thursday, December 21, 2023

TRAFFIC IMPACT:

No traffic impacts are scheduled for next week along the Vermont Route 142 corridor.

CONSTRUCTION ACTIVITIES:

The construction of the temporary shoring tower between Piers 1 and 2 has been completed. The contractor will begin to advance structural steel over Pier 2 and to the shoring towers over the coming weeks. Additional measures to excavate were found to be required in the cofferdam prior to the placement of the concrete tremie seal and those measures were completed this week. The placement of concrete was rescheduled for today. The de-watering and subsequent operations of cutting piles and placing rebar cages have been rescheduled with the de-watering slated to begin middle/end of next week.

LOCATION:

The Hinsdale, NH to Brattleboro, VT bridge project will replace the existing twin truss bridges on New Hampshire Route 119 over the Connecticut River with a single, new structure approximately 1800′ long. On the Vermont side, the new structure will begin on Vermont Route 142 – about 1000′ south of the current intersection of VT 142 and NH 119. The new configuration will connect to NH 119 in New Hampshire east of the George’s Field Road/NH 119 intersection.

PROJECTED COMPLETION: Fall 2024.

View as Webpage

Contact Information:

Name – Bethany Oprendek

Phone – 802.267.4044