Construction Update
Brattleboro-Hinsdale
BF A004(152)
DATE: Thursday, November 30, 2023
TRAFFIC IMPACT: No traffic impacts are scheduled for next week along the Vermont Route 142 corridor.
CONSTRUCTION ACTIVITIES:
Crews will continue to clean out the pipe piles into early next week. Site work for the shoring tower along the riverbank near Pier 1 has begun and will continue. The shoring tower will be a temporary means to support the structural steel while Pier 1 is being constructed. The Pier 1 cofferdam is also scheduled for construction to begin next week along with the water filtration system of tanks that will be used to treat the groundwater at Pier 1 once the excavation has concluded and dewatering can begin. The soil and the groundwater at this location will both need to be managed and mitigated due to known contaminants in the old fuel yard.
LOCATION:
The Hinsdale, NH to Brattleboro, VT bridge project will replace the existing twin truss bridges on New Hampshire Route 119 over the Connecticut River with a single, new structure approximately 1800′ long. On the Vermont side, the new structure will begin on Vermont Route 142 – about 1000′ south of the current intersection of VT 142 and NH 119. The new configuration will connect to NH 119 in New Hampshire east of the George’s Field Road/NH 119 intersection.
PROJECTED COMPLETION: Fall 2024.
Contact Information:
Name – Bethany Oprendek
Phone – 802.267.4044
Email – bethany@bbo-enterprises.com