Construction Update Brattleboro-Hinsdale Bridge Oct 25, 2023

Construction Update

Brattleboro-Hinsdale

BF A004(152)

DATE: Wednesday, October 25, 2023

TRAFFIC IMPACT: Vermont Route 142 is open, and no work that might delay traffic is scheduled for next week. No traffic control is planned.

CONSTRUCTION ACTIVITIES:

Crews have finished removing the foundations of the old tank system at the site where Pier 1 of the new bridge is to be built. A large crane and other equipment and materials have been mobilized to the site. Next week, driving the 30″ diameter steel pipe to bedrock using a diesel hammer, or pile driver, will begin. This very loud pounding is authorized from 7 a.m. to 7 p.m. Monday through Saturday and may last from three to five weeks. This is the last of the foundation work for this project

No work is currently scheduled up on the VT 142 corridor.

LOCATION:

The Hinsdale, NH to Brattleboro, VT bridge project will replace the existing twin truss bridges on New Hampshire Route 119 over the Connecticut River with a single, new structure approximately 1800′ long. On the Vermont side, the new structure will begin on Vermont Route 142 – about 1000′ south of the current intersection of VT 142 and NH 119. The new configuration will connect to NH 119 in New Hampshire east of the George’s Field Road/NH 119 intersection.

PROJECTED COMPLETION: Fall 2024.