DATE: Thursday, July 20, 2023

TRAFFIC IMPACT: Vermont Route 142 remains closed from the intersection with Royal Road north to the access to 28 Vernon Street until the end of August. Separate signed detours for cars and trucks are active. Local traffic should watch for concrete trucks entering and exiting the work zone in the coming weeks.

CONSTRUCTION ACTIVITIES: Work continues to progress on waterline and drainage installation from north to south along the VT 142 corridor. Ledge removal along the north end of the project with hydraulic hammers has become necessary to advance this work and will continue until elevations above the ledge line can be achieved. The raising of drainage structures will continue as grade of the highway is increased.

The layout and formwork for the northern MSE wall moment slabs will continue this week as the contractor prepares for concrete. The moment slabs will hold the railings and become the sidewalk. It is anticipated that these locations will be ready for concrete in the coming weeks.

The contractor has removed most of the debris that was caught up in the trestle and dewatered and cleaned out the Pier 2 cofferdam. This allows work on the bridge over the Connecticut River to continue. Delivery of steel girders to the site was able to resume this week as well.

DETOUR INFORMATION: The truck detour route from VT 142 will be up Cotton Mill Hill Road, left onto South Main Street, continuing onto Fairground Road, and finally back Canal Street. Cars detouring from VT 142 should proceed up Cotton Mill Hill Rd. and make a right hand turn onto South Main St. A turnaround has been constructed south of Cotton Mill Hill Rd. on VT 142 to allow vehicles to safely navigate this corridor. A three-way stop configuration has been implemented at the Cotton Mill Hill Rd. and VT 142 intersection.

LOCATION:

The Hinsdale, NH to Brattleboro, VT bridge project will replace the existing twin truss bridges on New Hampshire Route 119 over the Connecticut River with a single, new structure approximately 1800′ long. On the Vermont side, the new structure will begin on Vermont Route 142 – about 1000′ south of the current intersection of VT 142 and NH 119. The new configuration will connect to NH 119 in New Hampshire east of the George’s Field Road/NH 119 intersection.

PROJECTED COMPLETION: Fall 2024.