Construction Update Brattleboro-Hinsdale Bridge Oct 25, 2023
Crews have finished removing the foundations of the old tank system at the site where Pier 1 of the new bridge is to be built. A large crane and other equipment and materials have been mobilized to the site. Next week, driving the 30″ diameter steel pipe to bedrock using a diesel hammer, or pile driver, will begin. This very loud pounding is authorized from 7 a.m. to 7 p.m. Monday through Saturday and may last from three to five weeks. This is the last of the foundation work for this project
No work is currently scheduled up on the VT 142 corridor.