Construction Update Brattleboro-Hinsdale Bridge – April 18, 2024
One way alternating traffic patterns with flaggers will be implemented on Vermont Route 142 adjacent to the construction site on Monday and Tuesday next week. The northbound shoulder will be closed all week long and motorists are advised to watch for vehicles entering and exiting the construction site.
Delivery of steel to the abutment site on VT 142 is currently scheduled for Wednesday, April 24th, Monday, April 29th, and Wednesday, May 1st. The delivery route is planned to provide direct access from the south along VT 142 from Massachusetts Route 10. Flaggers and Uniformed Traffic Officers will be available to assist with the delivery, however it is not anticipated to require a lane closure. When the steel is ready to be moved from the truck to the bridge, a brief hold of all traffic on VT 142 will be required.