The recent weather has stalled steel delivery to the site, and the advance of structural steel across Pier 2 to the temporary shoring towers has been placed on hold until deliveries resume.
De-watering at the Pier 1 cofferdam continues to face ongoing challenges. The amount of water coming into the cofferdam is still too high a volume for the water treatment systems and the environmental permits. The contractor and engineering teams are analyzing the current systems in place to receive the site discharge as well as the configuration of the cofferdam to see what can be done to remedy this situation and continue with the work.
De-watering operation on hold pending further analysis.