RT 30 Will Remain Closed For A While Longer

Good Afternoon:
The work that necessitates the closure of RT 30 is wrapping up. We anticipate being able to reopen Rt 30 in approximately 2 hours. Apologies for this unavoidable inconvenience, and thanks again for your patience and understanding.

Cindy Cook
Public Information Officer
Brattleboro Bridge Replacement Project


RT. 30 Closed Longer Than Expected

RT 30 will be closed past 11AM today, because work is progressing more slowly than anticipated. We apologize for the inconvenience, and will let you know as soon as we’re able to reopen RT 30.

Thank you for your patience!

Cindy Cook
Public Information Officer
Principal, Adamant Accord, Inc.
Past Vice President, Association for Conflict Resolution


Rt 30 Closing July 9 Morning For I-91 Bridge Work

On Thursday, July 9, from 3:00 AM to 11:00 AM, a short section of VT Route 30 (where it crosses beneath I-91 in Brattleboro) will be closed. The closure is planned so that the project team can erect “traveler form” equipment that will be used to construct the new I-91 bridge in Brattleboro. Traveler forms are forms used to construct segmental cast-in-place concrete bridges.


Reminder: July 5 Exit 3 On Ramp Closure and Other Upcoming Closures

On Sunday, July 5, both the Northbound and Southbound Exit 3 On-Ramps will be closed from 11:00 AM to 6:00 PM to reduce congestion on I-91 Southbound caused by merging traffic. Because of highway logistics, we need to close both northbound and southbound on-ramps. Local southbound traffic will be rerouted to Route 5 south to Exit 1, and local northbound traffic will be rerouted on Route 5 north to Exit 4. Sheriff officers will assist in directing traffic.


I-91 Brattleboro Bridge Replacement Project Update: Week of July 5

I-91

On Sunday, July 5, both the Northbound and Southbound Exit 3 On-Ramps will be closed from 11:00 AM to 6:00 PM to reduce congestion on I-91 Southbound caused by merging traffic. Because of highway logistics, we need to close both northbound and southbound on-ramps. Local southbound traffic will be rerouted to Route 5 south to Exit 1, and local northbound traffic will be rerouted on Route 5 north to Exit 4. Sheriff officers will assist in directing traffic.


I-91 Bridge Project: Lane and Exit Closings July 12

The Southbound lane of I-91 between Exits 3 and 2 and the Exit 3 on-ramps will be closed to all vehicles on Sunday, July 12 from 5:00 AM to 9:00 AM to make it possible to conduct a routine bridge inspection. This time period was selected because it is the period of lowest traffic volume during the daylight hours needed to conduct the inspection.

Southbound traffic will be routed to Exit 1, and Northbound traffic attempting to use the Exit 3 on ramp will be routed north on Route 5 to Exit 4. Officers will be on hand to control traffic.

I-91 Northbound will remain open.


Brattleboro Bridge Replacement Project Update: Week of June 21 & Heads Up Regarding Fourth of July Weekend

I-91

On Sunday, July 5, both the Northbound and Southbound Exit 3 on-ramps will be closed from 11:00 AM to 6:00 PM to reduce congestion on I-91 Southbound caused by merging traffic. Because of highway logistics, we need to close both northbound and southbound on-ramps. Local southbound traffic will be rerouted to Route 5 south to Exit 1, and local northbound traffic will be rerouted to Route 5 north to Exit 4. Sheriff officers will assist in directing traffic.

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.


Public Invited to ‘Trail Talk’ To Be Held for I-91 Brattleboro Bridge Project

The PCL+FIGG Team will conduct the next on-site “trail talk” for the Public on Saturday, June 13, 2015. There has been a lot of progress at the I-91 Brattleboro Bridge project site, which will be shared with attendees. The talks will originate at the West River Trail near the marina. The trail talk will be led by Caleb Linn, Project Manager for PCL (lead contractor) and William Johnson, Senior Quality Engineer for FIGG (bridge designer).

Interested participants should meet the PCL+FIGG Team at the West River Trail trailhead on Saturday, June 13, 2015, at 8 a.m. and the talk will begin at 8:15 a.m. Participants will walk the trail to the I-91 bridge site, so please wear appropriate clothing and footwear.


I-91 Brattleboro Bridge Replacement Project Update: Week of June 7

The Strolling of the Heifers Weekend

We coordinated w/ the organizers, and hope that bridge construction did not affect the festival. We hope everyone had a wonderful time!

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.


I-91 Brattleboro Bridge Replacement Project Update: Week of May 31

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

Night work adjacent to Route 30 will continue this week, but will not affect traffic.

The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 will be reduced to a single lane intermittently both day and night, with flaggers regulating traffic within the work zone.


Red Clover Commons Work to Start on Thursday May 28th, 2015

Brattleboro Housing Partnerships and Housing Vermont are pleased to announce that demolition and environmental remediation work will begin at 30 Fairground Rd. on Thursday, May 28.

The work will focus on demolition of the block building toward the back of the lot, removal of materials still on the site and preparation of the entire area for construction. It is anticipated that the work will take at least two weeks.

Construction of the Red Clover Commons building and site will commence shortly after the demolition work is finished. The construction will take approximately 12 months. Once completed, residents from Melrose Terrace will begin to be moved to the new development.


I-91 Brattleboro Bridge Replacement Project Update: Week of May 17

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

Night work adjacent to Route 30 will continue this week, but will not affect traffic.

The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 will be reduced to a single lane intermittently both day and night, with flaggers regulating traffic within the work zone.


I-91 Brattleboro Bridge Replacement Project Update: Week of May 10

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

Night work adjacent to Route 30 will continue this week, but will not affect traffic.


Safety Improvement Project at Western Avenue, Union Hill, Cedar Street

A Safety Improvement Project at the intersection of Western Avenue, Union Hill, and Cedar Street will begin on Tuesday, May 5, 2015 with a projected completion in June, approximately six weeks. The Department of Public Works will be working on the project from 7:00 a.m. until 3:30 p.m. daily.

During this construction period, Union Hill and Cedar Street will be closed at the intersection and pedestrian traffic will be allowed via a temporary crosswalk.


I-91 Brattleboro Bridge Replacement Project Update: Week of May 3

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

Night work adjacent to Route 30 will continue this week, but will not affect traffic.

The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 will be reduced to a single lane intermittently both day and night, with flaggers regulating traffic within the work zone.


I-91 Brattleboro Bridge Replacement Project Update: Week of April 26

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

Night work adjacent to Route 30 will continue this week, but will not affect traffic.

The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 will be reduced to a single lane intermittently both day and night, with flaggers regulating traffic within the work zone.


I-91 Brattleboro Bridge Replacement Project Update: Week of April 19

I-91

On Tuesday, April 21, there will be a formal inspection of the I-91 Bridge. Daylight is needed for the inspection, so the bridge will be closed from approximately 8:00 AM to 5:00 PM. At the same time, the PCL team will repair potholes that developed over the winter. I-91 will be closed between Exits 2 and 3 both northbound and southbound. Traffic will be detoured onto VT Route 5.

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.


I-91 Brattleboro Bridge Replacement Project Update: Week of April 12

I-91

On Tuesday, April 21, there will be a formal inspection of the I-91 Bridge. Daylight is needed for the inspection, so the bridge will be closed from approximately 8:00 AM to 5:00 PM. At the same time, the PCL team will repair potholes that developed over the winter. I-91 will be closed between Exits 2 and 3 both northbound and southbound. Traffic will be detoured onto VT Route 5.

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.


I-91 Brattleboro Bridge Replacement Project Update: Week of March 29

New Text Alert System

A new text alert system for the Brattleboro Bridge Replacement Project makes it possible to receive text notifications of:

• Interstate ramp closings,

• Closings of I-91,

• Closings of VT Route 30 (but not single lane closings of Rt 30), and

• Any other situations regarding time sensitive project-related traffic issues.

People can sign up for this service by texting 313131 with the keyword “I91Brat”, or by using the signup widget on the project website www.i91brattleborobridge.com.