Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.
Route 30
The speed limit on Route 30 near the work zone has been reduced to 40 mph. Project-related truck activity on Route 30 will continue. Route 30 may be reduced to a single lane intermittently, with flaggers regulating traffic within the work zone.
On Wednesday, July 13th and Thursday, July 14th, Route 30 under I-91 in Brattleboro will be closed from approximately 7:00 AM until 6:00 PM to ensure the safety of the traveling public while work occurs on the new bridge.
Upper Dummerston Road
Upper Dummerston may be reduced to a single lane intermittently, with flaggers regulating traffic within the work zone.
West River Trail
The West River Trail is open. There are intersections between construction access and the trail path, and users should exercise extreme caution at these intersections. As an additional safety precaution, users of the West River Trail are reminded to keep pets on a leash in this area.
A scaffold protection system is being erected on the trail at the bridge intersection to protect trail users from debris/dropped items from the segmental work overhead. Please use caution while passing through the scaffolding. The system restricts the overhead clearance to 8 feet.
West River
No impacts are anticipated.
Text Alert System
A text alert system for the Brattleboro Bridge Replacement Project makes it possible to receive text notifications of:
• Interstate ramp closings,
• Closings of I-91,
• Closings of VT Route 30 (but not single lane closings of RT 30), and
• Any other situations regarding time sensitive project-related traffic issues.
People can sign up for this service by texting 313131 with the keyword “I91Brat”, or by using the signup widget on the project website www.i91brattleborobridge.com.
Project Progress
Segmental construction at Pier 2 has begun and will continue through the summer.
The new bridge deck over Upper Dummerston is complete, crews are backfilling and finishing the approaches.
The new roadway alignment and paving will continue through the summer.
Trail Talks
The next trail talk will be held July 9TH. Interested participants should meet the PCL+FIGG Team at the West River Trail trailhead at 8 a.m. and the talk will begin at 8:15 a.m.
Safety
Please focus on safety when driving through the construction work zone and remember that it is now against the law for drivers to use a hand-held cell phone.
For More Information
If you would like additional information, or would like to add others to this distribution list, please contact Bonnie Clark, Public Relations Officer, at bclark@pcl.com.