I-91 Brattleboro Bridge Replacement Project Update: Week of February 22

UPCOMING I-91 CLOSURE NORTHBOUND & SOUTHBOUND: Wednesday Night (2/18) 7:00 pm – 6:00 am and Thursday Night (2/19) 7:00 pm – 6:00 am.

Night work on the new bridge will continue at Route 30. Night work will be conducted Sunday night, February 22nd thru Friday night, February 27th (weather dependent).

I-91

Northbound I-91 traffic has been relocated onto the southbound bridge. Traffic will remain reduced to one lane in each direction on I-91 until completion of the new bridge. The new bridge will be 104’ wide and is designed to carry all four lanes of traffic –two northbound and two southbound.

Route 30

The speed limit on Route 30 near the work zone has been reduced to 40 mph. This reduction will remain in effect through the Spring of 2016.

Project-related truck activity on Route 30 will continue. Route 30 will be reduced to a single lane intermittently both day and night, with flaggers regulating traffic within the work zone.

Night work on the new bridge will resume at Route 30. Night work will be conducted Sunday night, February 22nd thru Friday night, February 27th (Weather dependent).

Upper Dummerston Road

The project will not affect traffic on Upper Dummerston Road the week of February 22nd.

West River Trail

The West River Trail is now open. There are intersections between construction access and the trail path, and users should exercise extreme caution at these intersections. As an additional safety precaution, users of the West River Trail are reminded to keep pets on a leash in this area. Trail users should be aware that snow removal operations on I91 may cause snow to fall on the trail.

West River

The northbound bridge over the West River has been removed. No project-related impacts to recreational boaters are anticipated for the week of February 22nd.

Project Progress

· The northbound structures have been entirely demolished.

· The new Bridge 9 Pier 1 and Pier 2 foundations are complete.

· The Bridge 9 arched columns at Pier 1 adjacent to VT RT 30 are complete. Construction of the Pier 2 arched columns are nearing completion.

· The Bridge 9 superstructure construction has started and will continue for the next two years.

· The new roadway alignment construction began last month. This work will be performed during the 2014 and 2015 non-winter seasons.

· Abutment work for the new Bridge 8 over Upper Dummerston Road has begun and will continue through the winter.

Trail Talks

We will continue to hold monthly trail talks for the community. The next Trail Talk will be held on February 21st.

Safety

Please focus on safety when driving through the construction work zone and remember that it is now against the law for drivers to use a hand-held cell phone.

For More Information

If you would like additional information, or would like to add others to this distribution list, please contact Cindy Cook, Public Relations Officer, Adamant Accord, Inc. ccook@adamantaccord.com.

Cindy Cook
Principal, Adamant Accord, Inc.
Past Vice President, Association for Conflict Resolution

PO Box 2
Adamant, VT 05640
ccook@adamantaccord.com
www.adamantaccord.com
Office: 802-223-1330
Cell: 802-272-2829

Leave a Reply