August 15, 2014
NOTICE TO THE PUBLIC
Milling of three streets was completed on Thursday and clean up around structures and along curb lines is taking place as planned on Friday. Resurfacing has been pushed back to Wednesday and Thursday, August 20-21. The tentative schedule has Lane Construction starting on Cotton Mill Hill, followed by Fairground Road and Birge Street. The second day would be Chapin, Grove Street and finally on Guilford Street. This can change with rainy weather between now and then.
Milling and paving on Western Avenue is scheduled for the night of Friday, August 22 with a rain date of Saturday, August 23. Lane Construction plans to do all work in one night using a large crew of people, starting at 6pm and continuing thru the night into early morning. The work area is between Brattle Street and Edward Heights. Motorist can expect delays.
Brattleboro Public Works