Construction Update
Brattleboro-Hinsdale
BF A004(152)
DATE: Thursday, October 24, 2024
TRAFFIC IMPACTS:
One-way alternating traffic controlled by flaggers will continue as needed on Vermont Route 142 near the construction site entrance to the new bridge. Motorists should be vigilant of uniformed traffic officers and vehicles with flashing lights protecting sign installers along all approach routes to the bridge.
CONSTRUCTION ACTIVITIES:
Crews will begin to install the traffic signals needed for the project beginning Monday, October 28th. Sign crews will begin placing signs for the new bridge next week as well. The signs will be covered until the bridge is ready to open. This crew will be accessing shoulders along approach routes to the project in a mobile work zone with a uniformed traffic officer.
Clean up continues on all parts of the project while the contractor removes overhang forms and strips, patches (if needed), and waterproofs exposed concrete. Removal of the temporary trestle, with its intermittent noise from the diesel hammer, is an ongoing process.
LOCATION:
The Hinsdale, NH to Brattleboro, VT bridge project will replace the existing twin truss bridges on New Hampshire Route 119 over the Connecticut River with a single, new structure approximately 1800′ long. On the Vermont side, the new structure will begin on Vermont Route 142 – about 1000′ south of the current intersection of VT 142 and NH 119. The new configuration will connect to NH 119 in New Hampshire east of the George’s Field Road/NH 119 intersection.
Unanticipated delays at a couple of the piers have adjusted the project completion date from Fall 2024 to Summer 2025.
PROJECTED COMPLETION: June 30, 2025