The project team is planning to close Upper Dummerston Road tomorrow morning, February 22 at 8:00 am. Due to the weather that may be coming tomorrow night and lasting through Thursday, we MAY open the Upper Dummerston Road tomorrow night and then close it again for a day or two when we can resume erection later this week or early next week. We will keep you posted as plans develop.
Cindy Cook
Principal, Adamant Accord, Inc.
Past Vice President, Association for Conflict Resolution
(As noted previously, the team needs three days for girder erections, and
the work is weather dependent. So if the predicted storm comes through,
Upper Dummerston Road will be opened when weather gets bad, and then
closed again to allow work to be completed.)